A site to gather community of Palmyra Residences, Balik Pulau, Penang
Sunday, May 29, 2011
Almost Done?
Called up Belleview last week. The lady mentioned that Vacant Possession is this month end (but it's month end tomorrow!) and OC will be ready in a month or 2. So everybody, start to allocate some budget to pay for your homeloan!
Sunday, March 6, 2011
6th March 2011 Visit
Finally we had some time to drive to Balik Pulau to see the latest updates on Palmyra. Our Proton Exora did pretty well going up and down the winding road, but that would mean the fuel expenses will increase 3 fold once we move to Balik Pulau.

There are not many lots left. The guys there said the project will be completed this June. That would means ka ching ka ching ka ching get ready for $$$$ reno, furnitures, home loan, moving cost etc etc. In my memory, the rooms were much bigger but looks like they have shrunk during this visit :)
Need to start thinking how to renovate the house since it's getting nearer:
Any good ideas???

There are not many lots left. The guys there said the project will be completed this June. That would means ka ching ka ching ka ching get ready for $$$$ reno, furnitures, home loan, moving cost etc etc. In my memory, the rooms were much bigger but looks like they have shrunk during this visit :)
Need to start thinking how to renovate the house since it's getting nearer:
- to setup a balcony, where to put the door? One side will block your location of the dressing table and the other side will block your bed.
- should we hack the wall between the kitchen and the "laundry" area so that there's bigger space?
- can we move the location of the "maid's room" door to the dining area and make it into kid's playroom (though it's pretty small)
- the upstairs 2nd & 3rd room, there are some pathetic space outside. It is currently placed with the aircond condensor. Can we hack the room to get a few inches more of space?
Any good ideas???
Friday, July 16, 2010
Updates 16th July 2010
It has been some time since we visited Balik Pulau (sounds so far away right, how to stay there next time?). Since it's durian feasting season, we decided to give Palmyra a visit to see the completion status. You can actually see the "shape" of the houses now...
Asked the sales person on expected completion, she mentioned somewhere mid next year. Woooo, time to start planning to pay the installment now that BLR is ever increasing, not to mention sugar, petrol and gas!
Tuesday, March 9, 2010
Completion of Foundation
We received a copy of letter today, asking the bank to release 10% payment as the foundtaion of the building has been completed.
There are 14 units of 2 Storey Terrace House altogether reaching the same stage.
Have not been driving to the other side of the island for some time. Still thinking that it's too far. Must get start to get used to it!
There are 14 units of 2 Storey Terrace House altogether reaching the same stage.
Have not been driving to the other side of the island for some time. Still thinking that it's too far. Must get start to get used to it!
Sunday, January 3, 2010
Updates 3rd January 2010
Here's the latest construction progress. The prices are RM416k for 20x62 and RM424k for 20x64 (if I remember correctly). There are few units left....